What Goes in a Planning Pack vs a Building Regulations Pack?

Planning permission and building regulations approval are two entirely separate processes requiring different document packs, and understanding what goes in each is essential for any architect managing a project from concept to construction.

One of the most persistent points of confusion in architectural practice – for students, clients, and even early-career architects – is the difference between planning permission and building regulations approval.

These are two entirely separate statutory processes. They have different purposes, different audiences, different documents, and different timelines. Conflating them causes real problems on live projects, from invalid applications to programme delays and abortive work.

This guide sets out clearly what goes into each pack, why those documents are required, and how to manage both processes efficiently across the life of a project.

What Goes in a Planning Pack vs a Building Regulations Pack?

What Is a Planning Pack?

A planning pack is the collection of documents submitted to a local planning authority (LPA) to gain permission for what can be built, where it can be built, and how it will look in context.

Its focus is primarily visual, contextual, and policy-driven. It is concerned with land use, appearance, impact on neighbours, heritage, ecology, and the relationship of a proposal to its surroundings – not with how it will be constructed.

Launch price £99

Start and run your whole practice from one place.

Pipeline, pricing, cash flow, clients and the weekly routine that holds it together. Seven hosted tools and 58 practical resources, in one private workspace.

See what’s inside £99 £147 one-time payment  ·  30-day refund

Who Reviews a Planning Pack?

Planning applications are assessed by planning officers employed by the LPA. They evaluate submissions against local development plan policies, national planning policy frameworks, and any specific designations affecting the site – such as conservation areas, green belt, or flood zones.

In some cases, applications are also referred to planning committees made up of elected councillors who make the final decision. Third parties, including neighbours, statutory consultees, and amenity societies, may also submit representations.

When Is a Planning Pack Required?

Full planning permission is required when a proposal falls outside permitted development rights. This includes most new-build dwellings, extensions beyond certain size thresholds, changes of use, and works in designated areas such as conservation areas or national parks.

Understanding early whether your project triggers full planning permission – or whether permitted development applies – is a fundamental part of the architecture design process. Getting this wrong at the outset can cost significant time and fees.

What Goes in a Planning Pack vs a Building Regulations Pack?

Core Documents in a Planning Pack

The exact content of a planning pack varies by project type and site constraints, but there is a core set of documents that almost every application requires. Each serves a specific function within the LPA’s assessment process.

Application Forms and Ownership Certificates

All planning applications in England are submitted through the Planning Portal. The application form captures basic information about the site, the applicant, the nature of the development, and any associated fees.

Ownership certificates must also be submitted, declaring whether the applicant owns the land, and confirming that any other owners or agricultural tenants have been formally notified of the application. Incorrect certificate declarations are a common cause of invalid submissions.

Location Plan and Site Plan

The location plan – typically drawn at 1:1250 or 1:2500 scale and based on an Ordnance Survey base – establishes the site within its wider context, with the application site boundary outlined in red and any other land in the applicant’s ownership outlined in blue.

The site plan, usually at 1:500 or 1:200 scale, shows the proposed development in relation to the site boundary, existing structures, and immediate surroundings. Understanding how to produce a compliant architectural site plan is a core technical skill that should be developed early in training.

Existing and Proposed Drawings

Planning submissions require drawings showing existing conditions alongside proposed changes. This typically means floor plans, elevations, and sections – all clearly labelled to distinguish existing from proposed.

These drawings do not need to carry the same level of technical detail as building regulations drawings. Their primary purpose is to communicate design intent, scale, massing, and appearance to planning officers and the public.

Refer to guidance on architectural elevation drawings to understand the conventions involved.

Design and Access Statement

A Design and Access Statement (DAS) is required for most major applications and for any application in a designated area. It sets out the design rationale, explains how the proposal responds to its context, and describes how access has been considered for all users.

A well-written DAS demonstrates that the design is not arbitrary – it shows the LPA how the proposal evolved and why the decisions made are appropriate. It should be read alongside the architecture design brief as part of the overall narrative.

Heritage, Ecology, and Supporting Reports

Depending on the site and proposal, a planning pack may need to include a range of specialist reports. Common examples include heritage statements (for listed buildings or conservation areas), bat surveys, tree surveys, transport assessments, noise assessments, and flood risk assessments.

These reports are commissioned from specialist consultants and must be submitted with the application. Missing a required report is one of the most frequent causes of invalid planning applications – an issue discussed further in the common mistakes section below.

What Is a Building Regulations Pack?

Where a planning pack is about what can be built and how it will look, a building regulations pack is about how it will be built safely and to the required technical standards.

The Building Regulations 2010 and their associated Approved Documents set minimum standards for structural integrity, fire safety, thermal performance, ventilation, accessibility, drainage, and more. A building regulations pack is the technical evidence submitted to demonstrate that a project will meet those standards.

Who Reviews a Building Regulations Pack?

Building regulations submissions are reviewed by a building control body – either the local authority building control (LABC) or a private approved inspector. Their role is to check technical compliance, not aesthetic merit or planning policy.

They will scrutinise drawings, specifications, calculations, and reports to verify that the proposed construction meets the requirements of each relevant Approved Document. They may also carry out site inspections at key stages during construction.

When Is a Building Regulations Pack Required?

Building regulations approval is required for most construction work, regardless of whether planning permission is also needed. This includes all new-build dwellings, most extensions, structural alterations, roof replacements, changes of use, and installations of new services such as electrical systems or drainage.

Critically, some projects require building regulations approval but not planning permission – and vice versa. They are independent processes, and one does not imply the other.

What Goes in a Planning Pack vs a Building Regulations Pack?

Core Documents in a Building Regulations Pack

A building regulations pack is substantially more technical than a planning pack. The drawings must carry far greater detail, and the submission must be accompanied by calculations and compliance reports that demonstrate adherence to the relevant Approved Documents.

Full Plans Application vs Building Notice

There are two main routes for building regulations submission. A full plans application involves submitting a complete set of drawings and supporting documents for checking before work begins – this is the recommended route for most projects as it provides a greater degree of certainty and a formal approval notice.

A building notice is a simpler notification process that does not require full technical drawings upfront. It is only appropriate for smaller, lower-risk domestic work, and it carries more risk as compliance is only verified during and after construction rather than before it begins.

Technical Drawings and Specifications

The drawings submitted for building regulations must show sufficient technical detail to demonstrate compliance. This means annotated construction details, wall sections, roof build-ups, foundation strategies, junction details, and material specifications – all drawn to appropriate scales.

Understanding how to develop and communicate this level of information is covered in detail in guides to construction details and working drawings. The gap in technical depth between planning drawings and building regulations drawings is significant and should never be underestimated.

Structural Calculations and Engineer’s Reports

Any project involving structural elements – new beams, altered foundations, load-bearing walls, new openings – will require input from a structural engineer. Their calculations and reports must form part of the building regulations submission.

This typically includes load calculations, beam sizing, foundation design, and details for connections and supports. Engaging a structural engineer early avoids the costly situation of redesigning elements because structural input arrives too late to influence the scheme.

Energy and Thermal Compliance Reports

Compliance with Part L of the Building Regulations – which governs the conservation of fuel and power – requires energy performance calculations. For new dwellings, this means a full SAP (Standard Assessment Procedure) calculation. For non-domestic buildings, a BRUKL report is required.

U-value calculations for individual construction elements such as walls, floors, and roofs must also be submitted to demonstrate that the proposed build-up achieves the required thermal performance. Attention to construction details at junctions – including the eaves detail and wall-to-floor connections – is critical for avoiding thermal bridging failures.

Fire Strategy and Access Compliance

Compliance with Part B (fire safety) requires documentation showing escape routes, travel distances, fire compartmentation, smoke control, and sprinkler provision where required. For more complex buildings, a full fire strategy document prepared by a fire engineer may be necessary.

Part M (accessibility) requires drawings and specifications demonstrating that the building is accessible to people with a range of disabilities. This includes entrance thresholds, door widths, sanitary facilities, and circulation routes – all of which must be shown in the technical drawings.

The level threshold detail is one of the most commonly checked elements at this stage.

What Goes in a Planning Pack vs a Building Regulations Pack?

Key Differences Between the Two Packs

It helps to view these two processes as serving entirely different purposes within the development system. Planning is concerned with place – with how a proposal affects its context, the environment, and the public interest.

Building regulations are concerned with performance – with how a building will be constructed to protect the health, safety, and welfare of its occupants.

The table below summarises the key distinctions across purpose, audience, content, and timing.

Planning pack: purpose is land use and design approval – audience is local planning authority and public – content focuses on context, appearance, and policy compliance – timing is early to mid-design stage.

Building regulations pack: purpose is technical and safety compliance – audience is building control body – content focuses on construction detail, specifications, and calculations – timing is mid to late design stage, typically after planning approval.

One further distinction worth noting is that planning approval lapses if not implemented within a fixed period (typically three years), whereas building regulations approval relates to the specific construction works as built and does not expire in the same way.

The Typical Sequence: When Each Pack Is Submitted

In most projects, planning approval comes first. Once consent is granted, the design is developed to the level of technical detail required for a building regulations submission. This sequence reflects the logic of moving from broader design decisions to detailed construction resolution.

However, the two processes can run concurrently on fast-track projects or where programme pressure demands it. Running them in parallel carries risk – if planning requires design changes, the building regulations package may need to be revised at cost.

Understanding the RIBA Work Stages helps situate each submission within a structured project timeline.

It is also important to understand that planning approval does not guarantee building regulations compliance. A scheme can be granted planning permission but still fail to meet building regulations requirements.

Both approvals must be obtained independently before construction can lawfully proceed.

Practical Guidance: Managing Both Packs on a Project

Coordinating two separate approval processes across a project requires systematic organisation. The following strategies help avoid the most common sources of delay and error.

Using a Document Register

Maintaining a structured drawing register is one of the most effective ways to keep track of which documents belong to which submission.

The register should record drawing numbers, revision status, submission dates, and approval status for both the planning and building regulations packages separately.

This becomes especially important on projects with long programmes, where drawings evolve significantly between the planning stage and the building regulations stage, and where consultants may be producing documents in parallel.

Coordinating Consultants Early

Structural engineers, energy assessors, fire engineers, ecologists, and heritage consultants all contribute documents to one or both packs. Engaging them early – ideally at concept stage – means their input can shape the design rather than be retrofitted to it.

Late consultant engagement is one of the leading causes of abortive work at both stages. A structural engineer’s foundation solution or a fire engineer’s escape route strategy can fundamentally affect the architecture if left too late in the process.

Understanding Conditions and Reserved Matters

Planning permissions are frequently granted subject to conditions. These conditions may require further information to be submitted and approved before work begins – for example, details of external materials, landscaping schemes, or archaeological investigations.

Discharging planning conditions is a separate process that runs alongside – and sometimes overlaps with – the building regulations stage. Failing to discharge conditions before construction starts is a legal risk that can invalidate the planning consent.

Understanding how conditions interact with the broader site analysis and design development process is essential for any project manager or lead architect.

Case Studies

Case Study 1: Residential Extension in a Conservation Area

A rear extension to a Victorian terraced house within a conservation area required a planning pack that included a heritage statement justifying the choice of materials and the design’s relationship to the host building.

The LPA required rendered elevations showing the proposal in context alongside samples of the proposed brick and lime mortar.

The building regulations pack for the same project required upgraded thermal detailing – because conservation area extensions are not exempt from Part L – and fire separation drawings to demonstrate that the new structure maintained adequate compartmentation between the existing and new elements.

Case Study 2: New-Build Dwelling – Outline to Full Approval

A new-build dwelling on a rural site first required outline planning permission to establish the principle of development on the land. The outline planning pack contained only basic access and layout information, with design details reserved for a later reserved matters application.

Once reserved matters were approved, the project moved into building regulations preparation. The full plans submission included structural calculations for the foundations and roof structure, a full SAP energy report, detailed wall and roof sections, and a drainage strategy.

The document set roughly trebled in volume between planning and building regulations stages.

Case Study 3: Change of Use – Office to Residential

The conversion of a redundant office building to residential use required a planning pack focused on policy compliance – demonstrating that the loss of employment space was acceptable under local plan policies and that the proposed residential use was appropriate for the location.

The building regulations pack for the same project was technically demanding. Compliance with Part E (sound insulation between dwellings), Part F (ventilation), Part B (fire escape from upper floors), and Part L (energy performance of the converted fabric) all required dedicated documentation. The fire strategy alone ran to several pages and required input from a specialist fire engineer.

Case Study 4: Commercial Fit-Out

A commercial tenant fit-out within an existing retail unit required no planning permission because the use class remained unchanged and no external alterations were proposed. The project could proceed without any planning pack whatsoever.

However, the fit-out required a full building regulations submission covering structural alterations to create a new mezzanine level, compliance with Part B for fire escape from the mezzanine, and Part M provisions for accessible sanitary facilities.

This case illustrates clearly that the two approval processes are entirely independent – planning silence does not mean building regulations compliance is not required.

Case Study 5: Listed Building Consent and Building Regulations

Works to a Grade II listed farmhouse required two parallel planning-side applications – full planning permission for the proposed extension, and listed building consent for the alterations to the historic fabric.

Both applications required a detailed heritage statement and were assessed by the conservation officer alongside the planning officer.

The building regulations pack for the same project required careful coordination with the heritage requirements. Certain insulation strategies acceptable under Part L would have caused harm to the historic fabric.

The energy assessor, structural engineer, and conservation architect worked together to find solutions that satisfied both building regulations compliance and the conditions of listed building consent – a process that requires early and sustained consultant engagement to resolve without abortive work.

Common Mistakes to Avoid

Both processes are well-documented, but errors remain common – particularly among those new to managing projects through the statutory approval system.

Assuming Planning Approval Covers Building Regulations

This is the most fundamental misconception. Planning approval means that the LPA has agreed to the principle and appearance of the development. It says nothing about whether the project can be safely built. A separate building regulations submission is always required unless a specific exemption applies.

Clients in particular often assume that once planning is granted, the project is approved and construction can begin.

Architects must be clear about this distinction from the first client meeting – a useful prompt when considering the questions to ask clients in architecture at the outset of a commission.

Submitting Insufficient Technical Detail at Building Regulations Stage

Drawings produced for planning are rarely sufficient for building regulations without substantial further development. Planning drawings communicate design intent. Building regulations drawings must demonstrate technical compliance in specific, annotated detail.

Submitting planning-level drawings to building control is a common source of rejection and delays. The technical development required between the two stages represents a significant portion of the architectural workload on any project.

Missing Specialist Reports at Planning Stage

Submitting a planning application without a required supporting report – a bat survey where one was clearly needed, or a flood risk assessment on a site in Flood Zone 2 – results in an invalid application. The LPA will not begin its assessment until all required documents are present.

Scoping what reports are needed should happen during desktop site analysis and pre-application engagement with the LPA. Leaving report commissioning until after the application is submitted causes avoidable delays that affect the entire project programme.

Conclusion

Planning permission and building regulations approval are two distinct statutory processes, and the document packs required for each reflect their fundamentally different purposes.

Launch price £99

Start and run your whole practice from one place.

Pipeline, pricing, cash flow, clients and the weekly routine that holds it together. Seven hosted tools and 58 practical resources, in one private workspace.

See what’s inside £99 £147 one-time payment  ·  30-day refund

A planning pack presents a proposal to the LPA for assessment against policy. A building regulations pack demonstrates to building control that a project will be built safely and to the required technical standards. Neither replaces the other, and neither guarantees the outcome of the other.

Understanding what goes into each pack – and when – is an essential skill for any architect managing projects through the development system.

Preparing both packs systematically, engaging consultants early, and maintaining a clear document register will reduce delays, avoid abortive work, and give both approval processes the best possible chance of running smoothly.

A free guide for architects going independent

Find the work before you need it.

Nobody hands you the first project. 16 routes to independent work, whether you’re running a side hustle, building towards the leap, or newly out on your own.

Download the guide Free

instant access newsletter signup unsubscribe any time

As seen on:

Unlock access to all our new and current products for life.

How Architects Find Their Own Work

16 routes to independent work. Whatever stage you’re at.

Enter your email for instant access.